- Amit Shah unveils bust of Ajit Pawar in Pune; reveals the 'secret' behind his entry into Mahayuti
- Anbumani Ramadoss seeks urgent recruitment as TN govt colleges face faculty shortage
- Trinamool infighting: Ritabrata faction's X account suspended, blames Mamata group
- Apple Smart Glasses May Launch in 2027, Takes on Meta Ray-Bans
- Mahesh Babu’s Varanasi Team Teases A Massive Update
- Adani Group a hard-asset play, Jefferies bullish on six firms amid $51 billion capex
- Drought forcing K'taka farmers to sell cattle at throwaway prices: BJP
- Jay Shah Reappointed As ICC Chairman For Second Term, Elected Unopposed
Rs 30,491-cr Amaravati ORR takes shape
In Short
Set to become new economic spine for capital region

Rs 30,491-cr Amaravati ORR takes shape
Amaravati: The Rs 30,491-crore Amaravati Outer Ring Road (ORR) is emerging as one of the largest infrastructure projects shaping the future economic geography of the capital region, with the National Highways Authority of India (NHAI) now restructuring the 195.13-km corridor into four mega construction packages and land acquisition progressing across five districts.
The project comprises a 189.93-km six-lane access-controlled ORR and a 5.2-km four lane spur between Nara Koduru and Budampadu, near Guntur. The alignment passes through about 97 villages in 23 mandals across NTR, Eluru, Krishna, Guntur and Palnadu districts. NHAI has proposed acquisition of nearly 7,400 acres for the corridor. The scale of investment is substantial. Of the Rs 30,491 crore project cost, Rs 10,595.70 crore is estimated for civil works and Rs 5,315 crore for land acquisition.
The balance covers environmental and forest clearances, utility shifting and other expenditure, including interest payments over 15 years under the Hybrid Annuity Model (HAM).
The four packages will incorporate major engineering works. Package-I, beginning near Kanchikacherla on the Vijayawada-Hyderabad highway and extending towards Mylavaram, will have 2.68-km and 1.64-km tunnels. Package-II covers 56 km up to Kolavennu. Package-III includes a 4.8-km Krishna River bridge at Vallurupalem and the Nara Koduru-Budampadu spur. Package-IV includes a 3.15-km Krishna bridge at Munnaluru and a 400-metre tunnel at Perecherla.The business significance of the corridor lies in its ability to take long-distance and freight traffic away from congested Vijayawada and Guntur, while providing faster links between Amaravati, surrounding national highways, industrial areas and the Gannavaram airport. By creating an access-controlled outer route, the ORR is expected to strengthen the region’s logistics network and provide improved connectivity for future industrial, commercial, residential and warehousing development along suitable interchanges.
The project has already undergone significant scope rationalisation. Its original estimated cost of Rs 38,450 crore has been reduced to Rs 30,491 crore after dropping a proposed 17.5-km Tenali-Kaja spur and the outer service roads, besides restricting the tunnel design to the six-lane requirement. The number of construction packages has also been reduced from the earlier proposal of six to eight.
The tunnel decision, however, has a long-term implication. Earlier proposals envisaged tunnels capable of accommodating future eight-lane expansion. Under the revised six-lane design, widening at the three tunnel locations would not be feasible without constructing new tunnels, according to the officials.
Land acquisition, which began in 2025, is progressing, with NHAI having issued draft notifications in the affected districts. The State has also facilitated the project by approving free supply of fly ash required for ORR construction.
R&B Minister B C Janardhan Reddy reviewed the land acquisition and project progress with NHAI officials last week, while associated connectivity projects, including the four-laning of Vinukonda-Guntur NH-544D and the proposed Guntur-Nizampatnam highway, are also moving ahead.
Together, these corridors are expected to create a wider transport network around Amaravati, reducing pressure on existing urban roads while providing the infrastructure base for the capital region’s next phase of economic expansion.
PM Modi arrives in Manila to attend ASEAN-India Summit and East Asia Summit
FM Sitharaman chairs 1st pre-Budget consultation with leading economists
Mekedatu Test for Vijay: Will He Take Up Tamil Nadu's Cause with Sonia
"It Was Between Modibhai and Me, Not Congress and BJP": Pitroda
Another Severe Cyclone Threatens AP; Fishermen Told Not to Venture into Sea till November 19
BJP-SAD alliance nears final shape: BJP seeks 40 seats; formal announcement likely on Nov 24