- Pavel Durov Jokes About Missing Telegram Groups in GTA 6
- Rahul Gandhi to visit Jaipur on Dec 9, Kharge to inaugurate training camp for new national secretaries
- PM Narendra Modi, Nepal PM Balen Shah Hold Bilateral Talks To Strengthen India-Nepal Ties
- PM Modi lauds India for crossing 1 crore HPV vaccine doses, calls it milestone in preventive healthcare
- Navigate the path of rational choices before giving wings to dollar dreams!
- Bullet train project hits electrification milestone
- Congress’s spin doctor perks up party cadre to aim for bigger mandate in TG
- Congress will win 90 Assembly seats: Revanth
CJI Surya Kant Recuses Himself from Supertech Insolvency Case, Cites Acquaintance with Applicant
In Short
CJI Surya Kant recuses himself from the Supertech insolvency case after revealing an applicant is remotely known to him. The Supreme Court will constitute a special bench to hear the matter involving 16 stalled projects and nearly 50,000 homes.

Chief Justice of India Surya Kant
Chief Justice of India Surya Kant has stepped aside from hearing a case involving 16 stalled Supertech projects, saying one of the applicants is remotely known to him. The Supreme Court will constitute a special bench to hear the matter.
CJI Surya Kant Steps Aside from Supertech Case
Chief Justice of India (CJI) Surya Kant on Monday, November 23, recused himself from a Supreme Court case concerning the monitoring and completion of 16 distressed Supertech housing projects undergoing insolvency proceedings.
Explaining his decision, the CJI said that one of the applicants was known to him, although they were not related. He described the connection as someone “remotely known” to him.
The matter was being heard by a bench comprising CJI Surya Kant and Justices Joymalya Bagchi and V Mohana. The Chief Justice said he would constitute a special bench to take up the case.
Supreme Court Concerned Over Slow Progress of Supertech Projects
The case involves 16 Supertech projects being executed by NBCC India Limited, the government's construction arm. Together, these projects account for nearly 50,000 housing units spread across Uttar Pradesh, Haryana, Uttarakhand and Karnataka.
The Supreme Court last heard the matter on October 27, when it considered an application filed by amicus curiae and advocate Rajiv Jain. Jain had requested the appointment of a court-monitored committee to supervise the completion of the projects.
The court had voiced its discontent with NBCC's slow progress with construction work during the last hearing. It considered the option of winding up the current committee and setting up a receiver like in Amrapali and Unitech.
Homebuyers Raise Questions Over NBCC's Role
NBCC has also faced criticism from homebuyers over its work on the projects. They pointed out that more than ₹30 crore had reportedly been spent on appointing the company as project management consultant, without a single tender being issued.
NBCC was appointed to oversee the 16 projects by the National Company Law Appellate Tribunal (NCLAT) in December 2024.
Currently, an Apex Court Committee (ACC), headed by former Supreme Court judge Justice (retired) Krishna Murari, is supervising construction. The committee also includes representatives from financial institutions, NBCC and real estate experts.
NBCC's RERA Exemption Plea Also Before Supreme Court
Separately, the Supreme Court is hearing NBCC's plea seeking exemptions under the Real Estate (Regulation and Development) Act (RERA) to complete the insolvency-hit projects.
In May, the NCLAT rejected NBCC's request for the exemption as well as its demand for higher fees from the sale of unfinished flats across the 16 projects.
The Supreme Court has also considered different options for taking the projects forward, including disbanding the existing committee and appointing an independent court-appointed receiver to supervise construction.