SCR commissions longest rail flyover

SCR commissions longest rail flyover
x
Highlights

  • The Gudur-Manubolu rail flyover is the 7th Rail over Rail across SCR
  • 2.2 km long flyover has been constructed as part of third line work between Gudur-Manubolu
  • This flyover facilitates cross-movement of trains between Vijayawada-Renigunta and Chennai to Vijayawada, without any detention of trains

Tirupati: South Central Railway has been continuously upgrading its rail infrastructure to ease train movements over its rail network for facilitating handling of more trains, while easing operational constraints. As part of this, a new rail flyover, Rail over Rail (RoR), has been constructed and commissioned between Gudur–Manubolu railway stations in Vijayawada division. This rail flyover has been constructed by Rail Vikas Nigam Limited (RVNL) as part of the third line works between Gudur-Manubolu.

The Gudur-Manubolu rail flyover is the 7th RoR across SCR. Stretching for a distance of 2.2 km, this is also the longest RoR in the zone. The previous longest rail flyover in the zone was only 40 metres.

The 2.2 km electrified RoR has been completed within two years with state-of-the-art technology.

The flyover consists of PSC (Pre-stressed Concrete) and composite girders which have inherent high torsional resistance and lower overall maintenance costs. In addition, high grade concrete and structural steel was used for the substructure, PSC girders and slab of the flyover.

Further, the dimensions of the bridge were planned in such a way that facilitated smooth execution of the project within the available railway land, thereby avoiding any land acquisition problems. This single line rail flyover between Gudur-Manubolu has been designed to handle traffic in both directions and is fit to handle trains with 32.5 tonne axle load.

Gudur railway station, located in the busy Grand Trunk Route, is an important interchange point between South Central Railway and Southern Railway handling all types of train movements. The new rail flyover will help ease the train movements in this saturated section. The commissioning of the rail flyover will facilitate simultaneous movements of trains between Vijayawada to Renigunta and Chennai to Vijayawada, while passing through Gudur station.

Previously, one of the train movements had to be stopped for facilitating movement in another direction. The simultaneous reception and dispatch facilities facilitated by the Rail Flyover will eliminate detentions on account of cross-movements, improve average speed of the trains and enhance operational efficiency of the train movements in the section.

Arun Kumar Jain, general, manager, SCR has complimented the officers and staff of team SCR and RVNL officials for constructing a rail flyover with state-of-the-art technology.

He stated that this kind of rail bridge is very much needed at Gudur station as the number of trains dealt at this station has been continuously increasing at this critical interchange point and a major junction.

Show Full Article