Inspection of ORR from Ghatkesar to Kandlakoya by Metropolitan Commissioner

Inspection of ORR from Ghatkesar to Kandlakoya by Metropolitan Commissioner
x
Highlights

ORR inspection by Metropolitan Commissioner on 26.05.2016 between 8.30am to 10.30am.

The Metropolitan Commissioner, HMDA Sri. Chiranjeevulu, I.A.S along with Project Director Smt. Sweta Mohanty, I.A.S. inspected stretches of Outer

Ring Road from Ghatkesar to Keesara (11.0Km) executed by M/s. NCC Limited: Keesara to Shamirpet (10.30Km) executed by M/s. Gayatri Project Ltd, Kandlakoya Interchange and illegal ramp connecting the Main Carriageway near Velimela.

Inspected the stretch of ORR from Ghatkesar to Keesara and instructed the Contractor M/s. NCC Limited to complete all balance works including Chainlink mesh, improve plantation for the Main Carriage Way by end of May, 2016.

Inspected the stretch of ORR from Keesara to Shamirpet and instructed the Contractor M/s. Gayatri Project Ltd to complete the balance works of Main

Carriage Way in all respects by end of May, 2016.

Further, the M.C, HMDA instructed the Contractor M/s KNR-GVR (JV) to complete the work at Kandlakoya Interchange on the Nagpur National

Highway the stay on which was recently vacated by Hon’ble Supreme Court to complete the balance 1.10Km of ORR at the earliest.

MC, HMDA instructed to examine the possibility of providing connectivity for the Velimela and Kollur residents to the Tellapur side of Outer

Ring Road and remove the illegal ramp as it may lead to accidents.