Centre tough on Ambani, takes back 5 KG-gas wells

Highlights

Centre Tough on Ambani, Takes Back 5 KG-Gas Wells, Oil Minister M Veerappa, Reliance Industries. Oil Minister M Veerappa Moily has approved taking away five gas discoveries from Reliance Industries in the KG-D6 block over the company's failure to meet timelines, but has allowed it to retain three other finds.

Oil Minister M Veerappa Moily has approved taking away five gas discoveries from Reliance Industries in the KG-D6 block over the company's failure to meet timelines, but has allowed it to retain three other finds.

The five discoveries - D4, D7, D8, D16 and D23 - hold 0.805 trillion cubic feet of reserves, or about one-fourth of the restated reserves in the currently producing Dhirubhai-1 and 3 (D1&D3) fields in KG-D6 block, and are worth USD 10 billion.
Moily in the October 9 order, however, agreed with RIL's contention that the company would retain D29, D30 and D31 gas finds, holding 0.345 TCF, to conduct tests for their confirmation, sources said.
RIL as per the contractual requirement of retaining only the area where discoveries have been made, had offered to give up or relinquish 5,367 square kilometres out of the total 7,645 sq km area in the eastern offshore KG-D6 block.
However, the Directorate General of Hydrocarbons (DGH) wanted another 1,130 sq km of area, which contained these 8 finds, to also be taken away from RIL on the grounds that the timeline to develop the fields had expired.
RIL and its partner BP plc officials on September 18 made a detailed presentation to the Minister, Oil Secretary Vivek Rae and DGH Director General R N Choubey contending that it had not deviated an inch from the Production Sharing Contract (PSC) and had the right to retain the 1,130 sq km area. Sources said Moily after examining the issue wrote on the file that, "the contractor should be asked to relinquish corresponding areas pertaining to 5 discoveries (814 sq km) with immediate effect" as RIL had not submitted the field development plan for these within the stipulated timeframe.
He wanted this area to be offered for bidding on a priority basis. For the balance three finds covering an area of 316 sq km, he agreed with RIL-BP that the DGH had not been insisting on drill stem test (DST) for confirmation of a discovery in the past and had decided to rake up the issue of absence of DST in case of D29, D30 and D31 finds after 8 months of commerciality documents being submitted and around 40 months from the discovery.
"There has been practice in the past not to insist for the DST for declaration of the commerciality (a prerequisite before investment plans are considered) by the DGH and a circular to that effect is still in existence," Moily wrote.