425 infra projects incur Rs 4.83-lakh cr cost overrun

Cost of implementation of 1,579 projects rose by 22.01% to Rs26,78,365.62 crore from Rs21,95,196.72 crore
New Delhi: As many as 425 infrastructure projects, each entailing an investment of Rs150 crore or more, have been hit by cost overruns of more than Rs4.83 lakh crore, according to a report.
According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs150 crore and above, out of 1,579 projects, 425 projects reported cost overruns and as many as 664 projects were delayed.
"Total original cost of implementation of the 1,579 projects was Rs21,95,196.72 crore and their anticipated completion cost is likely to be Rs26,78,365.62 crore, which reflects overall cost overruns of Rs4,83,168.90 crore (22.01 per cent of the original cost)," the ministry's latest report for March 2022 said. According to the report, the expenditure incurred on these projects till March 2022 stood at Rs13,88,760.73 crore, which is 51.85 per cent of the anticipated cost of the projects. However, the number of delayed projects decreased to 561, if delay is calculated on the basis of the latest schedule of completion.
Further, for 606 projects neither the year of commissioning nor the tentative gestation period has been reported. Out of the 664 delayed projects, 94 have overall delays in the range of 1-12 months, 124 have been delayed for 13-24 months, 331 projects for 25-60 months and 115 projects have been delayed for 61 months and above.
The average time overrun in these 664 delayed projects was 42.41 months. Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages. Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems are among the other reasons.















