Live
- ‘Get Set, Grow Summit 2024’ Focuses on Digital Detox for Families
- Stokes motivates his team to put in extra effort, says England pacer Potts
- From overcoming setbacks to leading India in U19 Women’s Asia Cup, Niki Prasad's amazing journey
- Driving Enterprise Security: Inside Venkata Reddy Thummala’s Leadership Journey
- Constitution debate: PM Modi hails 'Nari Shakti'; makes strong pitch for 'United Bharat’
- Abhijeet Bhardwaj: Revolutionizing Enterprise Analytics with Innovation and Expertise
- Bihar: Inquiry initiated against principal who went to buy veggies during school hours
- Press Sri Lankan Prez for release of Indian fishermen: TN Cong MP to EAM Jaishankar
- TN: DMK postpones executive meet due to heavy rains & Parliament session
- Porous silicon oxide electrodes can fix durability issues in batteries: Researchers
Just In
Teesta Barrage, Indira Sagar Poolavaram and Gosikhand irrigation projects are among five major water projects having strategic national importance that are way behind the completion mark, despite incurring expenditure over Rs 13,000 crore since 2008, according to the Comptroller and Auditor General of India
Teesta Barrage, Indira Sagar Poolavaram and Gosikhand irrigation projects are among five major water projects having strategic national importance that are way behind the completion mark, despite incurring expenditure over Rs 13,000 crore since 2008, according to the Comptroller and Auditor General of India.
Taking note of the cost escalation due to delays, the national auditor has observed that original cost estimate of the five projects was Rs 3,530 crore while the current cost estimate is Rs 86,172 cr.
Coming down heavily on Ministry of Water Resources, River Development and Ganga Rejuvenation, the CAG in its latest report observed that the poor implementation of the important projects was adversely impacting strategic national interests and not been able to reach a stage where the benefits of power generation, drinking water and reservoir creation can be delivered.
The five national water projects which are nowhere near the completion due to various reasons including poor contract management and administrative delays are Indira Sagar Polavaram project in Andhra Pradesh, Gosikhand irrigation project in Maharashtra, Shahipur Kandi dam in Punjab, Saryu Nahar Pariyojna in Uttar Pradesh and Teesta Barrage in West Bengal.
The primary objective of national projects is to enhance agricultural productivity by creating irrigation potential and water availability in covered areas. CAG noted that the shortfall in terms of physical progress in different components of the projects ranged from eight to 99 per cent in the five projects under implementation along with an overall cost escalation of 2,341 per cent that threatened the economic viability of the projects.
In February 2008, the Centre approved a scheme of national projects whereunder it identified 16 major water resource development and irrigation projects that were under the Accelerated Irrigation Benefits Programme (AIBP) but were languishing due to various constraints and hurdles including land acquisition, inter-State coordination, financial constraints and issues relating to rehabilitation and re-settlement of affected population.
Fundamental objective of the scheme was to ensure coordinated and focused action to expedite their execution and ensure their early completion. A performance audit of the scheme brought out that this fundamental objective remained unachieved though an expenditure of Rs 13,299.12 crore had been incurred on the five projects as of March 2017.
Out of the 16 national projects, only five projects with estimated Irrigation Potential of 25.10 lakh hectare were under implementation. In these five projects, 14.53 lakh hectare irrigation potential has been created but a mere 5.36 lakh hectare (37 per cent) irrigation potential is being utilised.
CAG has observed that the remaining 11 projects with estimated irrigation potential of 10.48 lakh hectare are yet to commence and are at different stages of approval.
The cost escalation in the five projects before their inclusion in the scheme was Rs 32,802 crore. However, since their inclusion as National Projects, two projects -- Indira Sagar Polavaram and Gosikhurd, had alone registered an escalation of Rs 49,840 crore over the previous escalation.
Remaining three projects have already overshot their approved completion time and none of them is near completion. CAG has pointed that the tardy implementation and cost escalation was attributable to management failures and deficiencies in terms of non-adherence to codal provisions relating to survey and investigations that are essential ingredients for preparation of 3 detailed project reports, ensuring statutory clearances for the project sites and administrative delays in land acquisitions.
This was compounded by inefficient Rehabilitation and Resettlement measures that further hindered progress of the projects. Deviation from codal provisions and tender/agreement terms provided no assurance as to the transparency and objectivity of the process of selection of contractors, award of works and their execution.
In none of the five projects under implementation had any proposal for Command Area Development works been sent to Central Water Commission for approval. CAG has also pointed out that the lack of adequate and effective monitoring and timely action to deal with breaches and damages to created infrastructure both contributed to the poor progress of works as well as inadequate maintenance of assets already created.
By Arun Kumar Das
© 2024 Hyderabad Media House Limited/The Hans India. All rights reserved. Powered by hocalwire.com