Live
- Rajadhiraaj: Love. Life. Leela
- Students immerse in nature in Chilkur forest
- Sri Aurobindo’s vision: Bridging the gap for holistic human evolution
- Sri Radha Govinda Ratha Yatra conducted
- A feast of music, dance and drama
- Mohan Babu denies absconding amid legal controversy
- Swift City to boost industrial growth in Bengaluru
- Allu Arjun walks out free after spending night in jail
- Congress harbours no grudge against any actor: TPCC chief
- Allu Arjun meets Upendra after release from prison, wishes for his ‘UI’ film
Just In
Andhra Pradesh trims housing target by 7 lakh
- Only 21 lakh houses to be built for the poor as against sanctioned 28.30 lakh
- Housing minister says Pedalandariki Illu (Housing for All) will be completed by March '24
- Devoid of funds, the state govt is linking the programme to various Central schemes like PMAY, MGNREGS and Jal Jeevan Mission, expecting to garner around Rs 25,000 cr for the first phase works
Vijayawada: The state government will construct only 21 lakh houses for the poor under its much-hyped 'Pedalandariki Illu' (Housing for All) programme, as against the 28.30 lakh originally sanctioned.
Housing minister Jogi Ramesh said, "We have distributed 30.20 lakh house sites and are building 21 lakh houses in two phases. The programme will be completed by March 2024."
He said 80 per cent of the houses were under construction now. The minister, however, did not elaborate why the scheme has been scaled down to 21 lakh from 28,30,227 houses as sanctioned in the year 2020.
In the first phase, 15.10 lakh houses were supposed to be built by June 2022 and, in the second phase, another 13.20 lakh by June 2023 at a total cost of Rs 50,944 crore. The government has, in fact, taken up 18,63,562 houses in the first phase but construction of over four lakh of those has not started even after a lapse of over 17 months.
As per the latest data of the housing department, only 1,52,325 of the 14.61 lakh houses (started) have been completed so far, with more than 8.30 lakh still stuck below the basement level.
Only in nine out of the 26 districts in the state, the house construction has at least reached the basement level.
As it is devoid of funds, the state government dovetailed its housing programme with various Central schemes like Pradhan Mantri Aawas Yojana, MGNREGS and Jal Jeevan Mission, hoping to garner about Rs 25,000 crore for the first phase works.
The state government was supposed to spend just over Rs 1,600 crore from its own coffers but is struggling to pool its resources.
Housing department officials cite many reasons for the poor progress in the programme, which the Y S Jagan Mohan Reddy government touts as its 'flagship.'
"Funds crunch obviously tops the list but non-availability of material, essentially sand, is another main dampener. Heavy rains over the last few months have also delayed the construction activity," a senior official of the housing department said.
For 'Pedalandariki Illu' in rural areas, there is a loan component of Rs 35,000 each. Only about 5.85 lakh beneficiaries could secure loan from the banks so far.
"In every village secretariat, we have entrusted the task to the welfare assistant to coordinate with the banks and facilitate the loan mobilisation process. We have involved the Society for Elimination of Rural Poverty also in this task," the housing department official said.
In districts like NTR, Krishna, Prakasam and Vizianagaram, the banks have so far delivered less number of loans.
This issue came up for discussion during a meeting between the state government and the bankers wherein the bankers were said to have cited the "poor progress of works" for limited disbursement of loans.
It is an interesting paradox in the urban areas that the beneficiaries are "reluctant" to take loans.
The bankers told the government that "poor progress of construction" was a major bottleneck in disbursal of loans for affordable housing. (PTI)